LRT-2 operation resumes after clearing of tree branches
LRT-2 operation resumes after clearing of tree branches
ABS-CBN News
Published May 09, 2017 07:20 PM PHT
|
Updated May 09, 2017 08:32 PM PHT

LRT2 full line operations suspended by 6:13 PM to give way for personnel to clear obstructions in the Anonas area. pic.twitter.com/zivMOJG8sw
— Hernando T. Cabrera (@attycabs) May 9, 2017
LRT2 full line operations suspended by 6:13 PM to give way for personnel to clear obstructions in the Anonas area. pic.twitter.com/zivMOJG8sw
— Hernando T. Cabrera (@attycabs) May 9, 2017
(UPDATE) - The whole operation of LRT 2 from Recto to Santolan resumed after a brief suspension due to tree branches hitting one train in the Anonas area, according to Light Rail Transit (LRT) spokesperson Hernando Cabrera.
(UPDATE) - The whole operation of LRT 2 from Recto to Santolan resumed after a brief suspension due to tree branches hitting one train in the Anonas area, according to Light Rail Transit (LRT) spokesperson Hernando Cabrera.
Operations of LRT-2 stations from Recto to Santolan were restored at 7:41 p.m.
Operations of LRT-2 stations from Recto to Santolan were restored at 7:41 p.m.
LRT2 full line operations resume at around 7:41 PM. Pasensiya na po sa abala.
— Hernando T. Cabrera (@attycabs) May 9, 2017
LRT2 full line operations resume at around 7:41 PM. Pasensiya na po sa abala.
— Hernando T. Cabrera (@attycabs) May 9, 2017
Operations of LRT-2 stations from Recto to Anonas were restored at 7:26 p.m.
Operations of LRT-2 stations from Recto to Anonas were restored at 7:26 p.m.
LRT2 Recto-Anonas operations restored at around 7:26 PM. Full line operations will resume anytime soon after subject area is fully cleared.
— Hernando T. Cabrera (@attycabs) May 9, 2017
LRT2 Recto-Anonas operations restored at around 7:26 PM. Full line operations will resume anytime soon after subject area is fully cleared.
— Hernando T. Cabrera (@attycabs) May 9, 2017
The Department of Public Works and Highways was doing road works when they accidentally hit a tree that fell on the side of the LRT's elevated tracks in the Anonas area, according to retired Gen. Reynaldo Berroya, LRTA administrator.
The Department of Public Works and Highways was doing road works when they accidentally hit a tree that fell on the side of the LRT's elevated tracks in the Anonas area, according to retired Gen. Reynaldo Berroya, LRTA administrator.
ADVERTISEMENT
LRT2 half line operations (Recto-VMapa only) since 4:03 PM. Tree branches hitting one train & obstructing the line. pic.twitter.com/qwV6VLE65e
— Hernando T. Cabrera (@attycabs) May 9, 2017
LRT2 half line operations (Recto-VMapa only) since 4:03 PM. Tree branches hitting one train & obstructing the line. pic.twitter.com/qwV6VLE65e
— Hernando T. Cabrera (@attycabs) May 9, 2017
Cabrera had announced the suspension at 6:13 p.m.
Cabrera had announced the suspension at 6:13 p.m.
"All passengers are safe. Will implement suspension of full line operations any time soon to give way for personnel to clear the area," Cabrera said.
"All passengers are safe. Will implement suspension of full line operations any time soon to give way for personnel to clear the area," Cabrera said.
All passengers are safe. Will implement suspension of full line operations any time soon to give way for personnel to clear the area.
— Hernando T. Cabrera (@attycabs) May 9, 2017
All passengers are safe. Will implement suspension of full line operations any time soon to give way for personnel to clear the area.
— Hernando T. Cabrera (@attycabs) May 9, 2017
--With a report from Raoul Esperas, ABS-CBN News